QUESTION 71
You are building a project plan in Microsoft Office Project Standard 2010.
You expand the project plan to display all outline levels and the project summary task.
You enter resources and their costs.
You have not yet set a baseline.
You need to estimate the total cost of the project.
What should you do?

Continue reading

Free Lead2pass 70-178 Brain Dumps is a Helpful Tool For You to Pass 70-178 Exam (61-70)

Lead2pass 70-178 material details are researched and created by the most professional certified authors who are regularly using current exams experience to create precise and logical dumps. You can get questions and answers from many other websites or books, but logic is the main key of success. And Lead2pass will give you this key of success.

QUESTION 61
You enter the finish date for a task, and then assign a resource.
You discover that the task is automatically scheduled for two weeks past the finish date you have entered.
You need to identify the problem.
What should you do?

Continue reading

Latest Update Free Version of Microsoft 70-178 Exam Dumps in Lead2pass (51-60)

Lead2pass is providing complete solutions for Microsoft 70-178 that will help the candidates learn extensively and score exceptional in the Microsoft ’s  70-178 exam. Passing the Microsoft is not a dream anymore as our user friendly learning resources ensure guaranteed success.

QUESTION 51
You manage a project that specifies all constraint types to As Soon As Possible.
You discover that one of your key tasks is scheduled to end prior to the targeted finish date.
You need to display the targeted finish date on the default Gantt chart.
What should you modify in the Task Information window?

Continue reading

Latest Update Free Version of Microsoft 70-178 Exam Dumps in Lead2pass (41-50)

The Lead2pass New Microsoft 70-178 practice tests helps the user to keep a check on their learning and understanding and improve for the Microsoft 70-178 exam. Lead2pass makes you pass your exam much easier.

QUESTION 41
All tasks in your project use the Auto Schedule mode. Several tasks are in progress.
You need to reschedule all the remaining work on the project.
You also need to achieve this goal without having rigid constraints set to your project’s tasks. What should you do?

Continue reading

Free Lead2pass 70-178 Brain Dumps is a Helpful Tool For You to Pass 70-178 Exam (31-40)

Lead2pass New Microsoft 70-178 brian dumps are designed to help you to out in a short time. You can get Lead2pass 70-178 brain dumps to pass your exam. To be a Microsoft professional makes you a better future.

QUESTION 31
Standard working hours are eight hours a day from Monday through Friday.
You create a task of fixed units and set the duration to 2 days.
You assign the task to John at 100 percent. John wants to work only 50 percent on the task.
You change John’s assignment units to 50 percent for the task.
Which set of values describes the specified task?

Continue reading

Free Lead2pass 70-178 Brain Dumps is a Helpful Tool For You to Pass 70-178 Exam (21-30)

The Lead2pass New Microsoft 70-178 practice tests helps the user to keep a check on their learning and understanding and improve for the Microsoft 70-178 exam. Lead2pass makes you pass your exam much easier.

QUESTION 21
You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart.
What should you do?

A.    Create a custom filter and a custom view.
B.    Create a custom table and a custom group.
C.    Create a custom filter and a custom table.
D.    Create a custom table and a custom view.

Continue reading

Latest Update Free Version of Microsoft 70-178 Exam Dumps in Lead2pass (11-20)

The Lead2pass New Microsoft 70-178 practice tests helps the user to keep a check on their learning and understanding and improve for the Microsoft 70-178 exam. Lead2pass makes you pass your exam much easier.

QUESTION 11
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource.
What should you do?

A.    Update the base project calendar.
B.    Change the working time for the resource.
C.    Change the maximum units for the resource.
D.    Assign the resource only to tasks that are scheduled on the working days.

Continue reading

Latest Update Free Version of Microsoft 70-178 Exam Dumps in Lead2pass (11-20)

The Lead2pass New Microsoft 70-178 practice tests helps the user to keep a check on their learning and understanding and improve for the Microsoft 70-178 exam. Lead2pass makes you pass your exam much easier.

QUESTION 11
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource.
What should you do?

A.    Update the base project calendar.
B.    Change the working time for the resource.
C.    Change the maximum units for the resource.
D.    Assign the resource only to tasks that are scheduled on the working days.

Continue reading